Projects has be done

Construction of Bidboland 2 Persian Gulf Refinery

Client:
Bidboland 2 Refinery – Sazeh Company

Project Location:
Behbahan, Khuzestan Province

Type of Project Activity:
Complete construction, installation, and pre-commissioning of Units 11 and 20 of the Bidboland 2 Persian Gulf Refinery, including underground and aboveground piping, fabrication, and installation of supports

Project Duration:
Twenty months

Bardsir Alloy Steel Project

Client:
Bardsir Alloy Steel Company

Project Location:
Bardsir, Kerman Province

Type of Project Activity:
Service operations, construction, installation, and commissioning of the entire steel plant

Project Duration:
Fifteen months

Sharif University Building Construction

Client:
Sharif University

Project Location:
Tehran Province

Type of Project Activity:
Construction, procurement, and complete execution of ten-story steel structure buildings and full finishing works

Project Duration:
Twelve months

Construction of the Persian Gulf Star Refinery

Client:
Faradast Energy Falat Company – Persian Gulf Star

Project Location:
Hormozgan Province

Type of Project Activity:
Complete construction, installation, and pre-commissioning of Units 01 and 02 of the processing unit of the Persian Gulf Star Gas Condensate Refinery, including underground and aboveground piping, steel structure fabrication, and full installation of static and rotating equipment

Project Duration:
Twelve months

Construction of 10-Inch Pipeline for Ilam Petrochemical

Client:
Khatam-al Anbiya Construction Headquarters – Ilam Petrochemical

Project Location:
Ilam Province

Type of Project Activity:
Execution of piping operations for the 10-inch West Ethylene Pipeline from Ilam to Piyazabad Village

Project Duration:
Six months

Construction of Bardsir Alloy Steel

Client:
Bardsir Alloy Steel Company

Project Location:
Bardsir, Kerman Province

Type of Project Activity:
Design, procurement, fabrication, and installation of 5 stainless steel line storage accumulators

Project Duration:
Four months

Construction of Mobadel Sazeh Esfahan Steel

Client:
Mobadel Sazeh Esfahan Company

Project Location:
Ardestan, Esfahan Province

Type of Project Activity:
Fabrication of MAPNA stacks related to the Shirvan Power Plant

Project Duration:
Twelve months

Construction of Milad Esfahan Steel

Client:
Milad Esfahan Steel Company

Project Location:
Esfahan Province – Milad Workshop

Type of Project Activity:
Fabrication of furnace shell, recuperator, charge winch, and related components for Neyriz Steel

Project Duration:
Twelve months

Esfahan Refinery

Client:
Esfahan Refinery Company

Project Location:
Esfahan Province – Esfahan Refinery

Type of Project Activity:
Repair, renovation, and replacement of mechanical equipment and piping across the entire refinery site

Project Duration:
Twelve months, year 2007

Shahid Rasouli Petrochemical

Client:
Shahid Rasouli Petrochemical Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 3

Type of Project Activity:
Installation of all equipment for Shahid Rasouli Petrochemical

Project Duration:
Six months

Arvand Petrochemical

Client:
Arvand Petrochemical Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 4

Type of Project Activity:
Fabrication and installation of all warehouses and steel structures for the PVC storage facility of Arvand Petrochemical

Project Duration:
Twelve months

Ilam HDPE Unit

Client:
Ilam Petrochemical Company
Oxin Sanat Company

Project Location:
Ilam Province – Ilam Petrochemical

Type of Project Activity:
Aboveground piping operations, support fabrication, and equipment installation for the E.P.D.H unit of Ilam Petrochemical

Project Duration:
Twelve months

Isocyanates Project Piping

Client:
Karoon Petrochemical Company
Tose’e Shabakeha Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 2

Type of Project Activity:
Installation and welding of alloy pipes and complete piping execution for the Karoon site, totaling approximately 100,000 inch-diameter

Project Duration:
Fifteen months

Marun Offsite Piping

Client:
Marun Petrochemical Company
Sazeh Khavar Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 3

Type of Project Activity:

  • Installation and welding of Marun Petrochemical offsite pipelines, approximately 118,000 inch-diameter (aboveground and underground)

  • Fabrication and installation of supports for offsite pipelines

Project Duration:
Seventeen months

Hydrotest

Client:
Marun Petrochemical Company
Sazeh Khavar Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 3

Type of Project Activity:

  • Punching, punch clearing, hydrotesting, and flushing operations for Marun Petrochemical offsite pipelines

Project Duration:
Five months

Miter Fabrication

Client:
Marun Petrochemical Company
Sazeh Khavar Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 3

Type of Project Activity:

  • Fabrication of 22,000 inch-diameter carbon steel and alloy pipe miters for Marun Petrochemical offsite pipelines

Project Duration:
Seventeen months

Fajr Offsite

Client:
Fajr Petrochemical Company
Tehran Jonoob Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 3

Type of Project Activity:
Installation and welding of alloy and carbon steel pipes, totaling 72,000 inch-diameter

Project Duration:
Ten months

Under Two-Inch Lines for Fanavaran Petrochemical AA & CO Unit

Client:
Fanavaran Petrochemical Company
Tehran Jonoob Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 3

Type of Project Activity:

  • Installation and welding of piping for CO and AA lines of the Steam Trap unit, totaling 115,000 inch-diameter (AG & UG operations)

  • Fabrication and installation of supports for Steam Trap lines

Project Duration:
Eleven months

Mojan Water Treatment Plant

Client:
Mojan Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 1

Type of Project Activity:

  • Execution of all piping operations for the water treatment plant

  • Installation of all equipment and accessories for the water treatment plant

Project Duration:
Eight months

Temporary 18-Inch Steam Line

Client:
Fajr Petrochemical Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 4

Type of Project Activity:
Installation and welding of alloy steel (alloy steel) pipes for the temporary 18-inch steam line

Project Duration:
Seven months

Fajr Petrochemical Tanks

Client:
Fajr Petrochemical Company
Oxin Sanat Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone

Type of Project Activity:
Fabrication and installation of 6 carbon steel atmospheric tanks with fixed and floating roofs, including painting and testing

Project Duration:
Twelve months

Cutting and Transportation

Client:
Tabriz Petrochemical Company

Project Location:
East Azerbaijan Province – Tabriz

Type of Project Activity:
Collection, cutting, grinding, and transportation of alloy steel pipes for the 18-inch steam line

Project Duration:
Two months

Steel Structure Fabrication

Client:
Milad Construction Company

Project Location:
Esfahan Province – Esfahan

Type of Project Activity:
Preparation of workshop drawings for 800 tons of steel structures
Fabrication of 800 tons of steel structures

Project Duration:
Eleven months

Hydrotest

Client:
Fajr Petrochemical Company
Oxin Sanat Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 4

Type of Project Activity:
Punching, punch clearing, hydrotesting, and flushing operations for Fajr Petrochemical offsite pipelines in Site 4

Project Duration:
Three months

Utility Flare Line

Client:
Fajr Petrochemical Company
Oxin Sanat Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 4

Type of Project Activity:
Piping operations for the flare line of Fajr Petrochemical Utility Unit, including welding and installation of carbon steel and alloy side lines connected to the main flare

Project Duration:
Four months

Feedstock and Product Lines

Client:
Petrochemical Special Economic Zone
Oxin Sanat Company

Project Location:
Khuzestan Province – Bandar Mahshahr Petrochemical Special Economic Zone – Sites 2, 3, 4, and 5

Type of Project Activity:
Offsite piping operations for permanent transfer lines of feedstock and products in the Special Economic Zone, including 30,000 inch-diameter welding of stainless steel pipes

Project Duration:
Sixteen months

Sari Wood and Paper Project

Client:
Ministry of Industries
National Industries Organization of Iran
Mazandaran Wood and Paper Industries Company

Project Location:
Mazandaran Province – Sari

Type of Project Activity:
Repair, replacement, and renovation of warehouse roofs; replacement, rust removal, and painting of steel structures; replacement of electrical and instrumentation cables and pipes; repair and renovation of static and rotating mechanical equipment

Project Duration:
Twelve months during the years 2002 and 2003

Fajr Offsite

Client:
Fajr Petrochemical Company
Oxin Sanat Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone, Site 4

Type of Project Activity:
Aboveground piping operations for Fajr Petrochemical, Site 4, including 28,000 inch-diameter welding and installation of stainless steel pipes

Project Duration:
Eighteen months

Khuzestan Petrochemical Tanks

Client:
Khuzestan Petrochemical Company
Oxin Sanat Company

Project Location:
Khuzestan Province – Petrochemical Special Economic Zone

Type of Project Activity:
Fabrication and installation of 4 stainless steel tanks and 2 carbon steel tanks, including painting and testing

Project Duration:
Nine months

Sari Wood and Paper Project

Client:
Ministry of Industries
National Industries Organization of Iran
Mazandaran Wood and Paper Industries Company

Project Location:
Mazandaran Province – Sari

Type of Project Activity:
Fabrication and installation of sprinklers (14,000 inch-diameter welding operations)

Project Duration:
Six months

Client:
Chaharmahal and Bakhtiari Telecommunication Company

Project Location:
Chaharmahal and Bakhtiari Province

Type of Project Activity:
Installation of four microwave telecommunication towers

Project Duration:
Seven months